Bloom Companies, LLC informs
Source: The Sangai Express
Tengnoupal, April 13 2023:
Bloom Companies, LLC has informed that the construction of NH-37 (Keithelmabi to Senam village) has significantly slowed down as the contractor tasked with the project namely M/s CMM Infra Projects has undergone insolvency and is under National Company Law Tribunal (NCLT) .
In a release, team leader of Bloom Companies, L N Ranjan informed that cure notice & notice for getting the work completed at the Risk and Cost of the contractor both have already been served to the contractor by NHIDCL.
It also stated that on April 11, 2023, an organisation from the Kotlane area raised the issue of serious health concerns to the locals by the spread of excessive dust from the road and announced a bandh along NH-37 .
It continued that to address the pressing issue of the National Highway blockade, a meeting was held on April 11 between the authorities and local stakeholders .
"NHIDCL has assured to commence water sprinkling from April 12.It was assured that the final decision regarding termination of the contract in accordance with the contract provisions will be intimated to locals after one week i.e on April 18, after due consultation with the Competent Authorities of NHIDCL", it asserted.