Planned shutdown
Source: The Sangai Express
Imphal, April 03 2025:
The Manipur State Power Company Limited has notified to all concerned that both the 33kV Gamphazol-Sekmai line and 33kV Leimakhong-Sekmai will be under shutdown from 10 am to 4 pm from April 4 to 7 (4 days) .
The planned shutdown is due to shifting work of the aforementioned lines at Sekmai near 33/11 kV Sekmai sub-station for the road expansion work of Imphal-Kohima Road (NH-39) by NHIDCL.
During this period, power supply to consumers of 33/11kV Sekmai sub-station will be affected, said the statement.
Additionally, in a separate notification, MSPCL has informed that there will be a planned shutdown of 33/11kV Sangaiprou sub-station from 7.30 am to 9.30 am on April 4 .
Consumers in the areas of Tera Lukram Leirak, Tera Sayang Pukhri, Tera Bazar, Yengkhom Leirak, Khanam Leirak etc will be affected by the power outage.