KSO pushes for early completion of Mini-Secretariat
Source: The Sangai Express
Imphal, May 19 2016 :
KSO, Churachandpur has conducted an inspection at the on-going mini-secretariat
construction site at Tuibuang and demanded that
construction work of some of the blocks should
be completed before September this year, re-
ports our correspondent.
Members of the student body visited the
construction site and witnessed only minimal
progress.
Nevertheless, representatives of the work
agency said that they are making relentless
effort complete two office blocks and 6 quar-
ter blocks by this September.
KSO stated that it will monitor the work
to ascertain the construction is completed on time.