Source: Hueiyen News Service
Imphal, July 23 2010:
Construction works of Thoubal Multi-purpose Project and Dolaithabi Project is targeting to complete by March 2012, said Irrigation and Flood Control (IFC) minister, N Biren today said in the House of the state Assembly.
Giving reply to a question raised by MLA N Mangi of CPI from the ruling bench, the minister said that 77 percent of the construction works of the Thoubal dam and 70 percent of spillway completed.
The construction works of left main canal from 0-25 km and 0-6 km for the right canal have been completed, the minister added.
The Dolaithabi Project is also targeting to commission by March 2012, the minister said adding that construction works of right side main canal of the Khuga Multi-purpose Project will also be completed by March 2011 .