Source: The Sangai Express
Imphal, June 30:
Consequent upon the improvement in the availability of power from the North Eastern Regional Grid, the current load shedding programme from 5 am to 5 pm and 10 pm to 1 am of the next day has been withdrawn with immediate effect, informed a press release issued by the SE , Transmission Circle, Department of Electricity.
According to a revised load shedding programme, there will be no load shedding between 5 am to 5 pm except for areas where sub-stations have capacity constraints.
However, there will be load shedding during 5 pm to 10 pm as per the existing roster system.
From 10 pm to 1 am of the next day, there will be no load shedding except for areas covered by sub-stations having capacity constraints.
Further, there will be no load shedding in Imphal areas from 1 am to 5 am except under sub-stations with capacity constraints.
But for other districts and outskirts of Imphal, the existing load shedding programme will remain unchanged.
The revised load shedding programme will be reviewed after 2 months.