Village authority condemns incomplete school construction work
Source: The Sangai Express
Kamjong, July 26 2019:
The students of Ningthi Junior High School are facing 'immense hardship' as the upgradation/construction work of the school remain incomplete even as the deadline for completion of the work has passed, said a statement of Ningthi Village Authority, Kamjong district Friday.
The work order was issued on November 29, 2016 .
The old wooden school building was torn down to construct new building at the same site.
According to 'reliable source the 1st and 2nd instalment money have been drawn by the contractor' but the work is yet to be completed, said the village authority.
Concerned with the students unable to attend school, it appealed the authority concerned to complete the construction at the earliest in the interest of the students.