Load shedding
Source: The Sangai Express
Imphal, December 14 2017:
Manipur State Power Company Limited has notified that 33KV transmission line from Yaingangpokpi to Hundong will remain shut-down on December 16 and 17 from 8:30 am to 4 pm on both days for jungle clearance work .
And 33KV transmission line from Jiribam to Rengpur will also be shut down from December 16 to 20 from 8 am to 3pm daily for routine line checking .
Consumers covered by the 33/11KV sub-stations Litan, Hundong, Ukhrul-Khunjao, Tolloi, Namrei, Jessami, Kamjong and Rengpur, Tamenglong and Khoupum area will not be able to avail power supply during the mentioned period said a statement issued by the office of Deputy General Manager, Transmission Division no II, Manipur State Power Company Limited, Lamphel.