Sub-contractor urged to clear pending bills
Source: Chronicle News Service
Imphal, March 06 2023:
Informing that the bills for construction materials and labour charges for construction of Manipur University international gents' and ladies' hostels are still pending, the supplier and masons have appealed to the sub-contractor concerned to clear the pending bill at the earliest.
Addressing a press meet at Manipur Press Club here on Monday, supplier S Raju informed that the project was executed by a sub-contractor named Jimmy Khor Jajou.
Work order was issued in 2016 and construction began in 2017.The hostel was handed over to MU authority after completion in 2022 .
However, the sub-con-tractor has failed to clear Rs 32 lakh related to supply of construction materials, and more than Rs 50 lakh for labour charges, he said while drawing attention of the authority concerned to look into the matter.