Incomplete work at Moreh auditorium
Source: The Sangai Express
Imphal, September 19 2011:
Exposing it to the vagaries of weather, construction work on an auditorium by the Government of Manipur for all communities living in Moreh has remained incomplete for over 5 years.
Construction work on the auditorium had been taken up at Moreh Ward no.2 .
But it has remained stalled for the last five years.
Exposure to the vagaries of nature all these years has also taken its toll on the structure.
A team of officials of Hill Tribal Council, Moreh led by its vice president H Mate today visited the work site for inspection and has drawn the attention of the Government of Manipur for ensuring completion of the auditorium at the earliest possible.