Irrelevance of 66 MW Loktak Downstream HEP in Manipur

Jiten Yumnam *

 leimatak River - to be submerged by proposed 66 MW Loktak Downstream Hydro project in Manipur
Leimatak River - to be submerged by proposed 66 MW Loktak Downstream Hydro project in Manipur



Media reported that the Loktak Downstream Hydroelectric Corporation Ltd has signed a Power Purchase Agreement (PPA) with the Manipur State Power Distribution Company Ltd (MSPDCL) for 66 MW Loktak Downstream Hydroelectric Project on 31st August 2020. According to the PPA, the Government of Manipur envisaged to purchase the entire power to be generated by the project .

The terms and conditions of PPA and cost of per unit power to be purchased by the Government remains concealed. For long, the Government refused to sign the PPA due to the high cost of the power per unit cost. The NHPC has long pressured the Government to sign the PPA for the project.

Introduction: The 66 MW Loktak Downstream Hydroelectric Project (LDP) project is proposed as a run of the river scheme intending to utilize the tail race discharge from the powerhouse of the 105 MW Loktak Multipurpose Hydroelectric project (Loktak HEP) along with the inflow of the River Leimatak for power generation.

A 28 meters high barrage over the Leimatak River near Tousang Khunou Village will be built for the project. The project cost is Rs. 867.77 crores as of 2006 . The project cost of LDP stands at Rs. 1250 crores by 2015 , which increased to Rs. 1391.65 Crores by December 2018.

After the MoU for the Loktak Downstream Project was signed between the Government of Manipur and the NHPC on 26 September 2008, the Loktak Downstream Hydroelectric Corporation Limited (LDHCL) was formed as a joint venture company of National Hydroelectric Power Corporation (NHPC) with stake of 74% and Government of Manipur with a stake 26% for implementation of the proposed project. The LDHCL is a subsidiary company of NHPC Limited .

The 59th meeting of Expert Appraisal Committee (EAC) of the Ministry of Environment and Forest and Climate Change, Government of India, held from 20th till 21st July 2012 recommended environmental clearance for the project . Concerns persists that the Stage - 1 Forest Clearance has been cleared to divert 211.50 hectares of forest on 3 March 2011 without adhering to Forest Rights Act, 2006 .

The LDHCL maintained that the total catchment area of the project span over 554 Sq.km and the land requirement is 211.50 hectares, including wet paddy fields on river bed of Leimatak River, agriculture land and forest, which affected communities, viz, Rongmei tribe rely for their subsistence.

Delays in PPA signing and JICA financing Plan: The initiation of the Loktak Downstream Project has been delayed as the NHPC and the Manipur Government failed to sign the power purchase agreement (PPA) till July 2020. The high power tariff of Loktak Downstream Project at around Rs 6.17 per unit as of 2017, was key reason for the refusal of Manipur Government sign the PPA.

In 2015, the former Power Minister of the Government of India earlier asked the Government of Manipur and NHPC to reduce the power tariff to Rs 5.30 per unit as Rs 400 crores would be given as grant by Central Government.

The NHPC in July 2006 LSO urged the Government of Manipur to relinquish its 12% free power entitlement from the 90 MW Loktak downstream power project to bring down the cost of the power and to optimize the estimated implementation cost and the electricity tariff for the project . In lieu, NHPC proposed that the state government may take up equity in the project.

For long, NHPC has been pressuring the Manipur Government to sign the PPA as soon as possible but the latter contended that the power tariff is higher than admissible. The Chairman and Managing Director (CMD), Mr. Joshi of NHPC again met the Chief Minister of Manipur, Mr N. Biren on 14 December 2017 pursuing for an early commencement of the construction of LDP over the Leimatak River .

However, the PPA was finally signed on 31st August 2020, with Manipur Government agreeing to purchase entire power from the project. Earlier, the Government of Meghalaya and Tripura signed PPA on 20 June 2003 and 19 June 2003 for purchase of power from the project.

In February 2018, media reported that the Government of India sought financial assistance from the Japan International Cooperation Agency (JICA), to fund the LDP. On pretext that the power tariff would be too high when the project is funded by the Government of India, an alternative of seeking the necessary fund from JICA has been explored .

The Government maintained that if the project is funded by JICA whose interest is exceptionally low, the power tariff can be reduced to Rs 5 per unit. The plan to pursue financing from JICA indeed laid bare the challenges in financing process of LDP.

Public Hearing: Earlier, an environment Public Hearing for the LDP project was conducted on 7 June 2011 at Longjang (Thangal) village in Tamenglong district, Manipur. The Environment Impact Assessment and Environment Management Plan has not been furnished. The project area falls in high seismic zone V. Civil societies attending the hearing expressed concerns with multifaceted impacts of the project.

Representatives of Zeliangrong Students Union, landowner of Toushang Village, Soubung village, Chakanglong Peidai, Taoshang village etc raised concerns at the hearing. Many villagers who attended the public hearing also expressed support to the project without gaining access to pertinent information on impacts of the project. Clearly, the adherence to free, prior, and informed consent of the affected communities remains another concern.

Impacts: The project authorities outlined that at least 705 families will be affected due to loss of their right over forest land for the LDP. The project authorities have been building the road from Tupul to Thangal Village for a total length of 97.91 kms to aid construction of the Dam, powerhouse, and pump House.

The forest areas required is 40.9 hectares for the road from Tupul to Dam site, for road from Dam site to Powerhouse and for diversion of forest for construction of road from Pump House to Irang River. Another 144 hectares of land has been identified for compensatory afforestation for the loss of 72 hectares of forest land at Thangal Village to be acquired for the road expansion for the project .

Earlier, a group of affected villagers of Taosang Village filed a case against the step taken by the Government for resurvey for which the Gauhati High Court stayed the same. The survey and other works were suspended for quite some time due to the Court's interventions .

The Citizens Concern for Dam and Development (CCDD) on 15 December 2017 condemned the pursuance of the Chairman and Managing Director of NHPC, in his meeting with Chief Minister of Manipur to commence construction of LDP. CCDD stated pursuance of LDP by using water discharge from Loktak project is a disregard of the call of people of Manipur to decommission Ithai Barrage of the Loktak HEP.

The release of water from Leimatak Power station of Loktak project affected the water flow of the Leimatak River. The LDP project will further worsen the downstream impacts of Ithai Barrage. A man identified Jianthailung Riame (28 yrs) s/o Langangdaipou Riamei of Soubunglong Part-II village under Khoupum Sub-Division of Noney district lost his life while crossing the Leimatak River in June 2020, as the river current turned violent due to opening of shutter of the Power Station of Loktak project .

The LDP will lead to further militarization as the project authorities insisted to raise four battalions of security forces to protect the project and to protect establishment of related infrastructures like road from Tupul to the project site at Thangal village.

As per the agreement between Government of Manipur and NHPC signed on 12 February 1999, provision of necessary security arrangement is the responsibility of Government of Manipur. One battalion of CRPF was to be deployed in the project area from 1 October 2000 to enable Border Road Organization build the Tupul to Thangal road. NHPC is slated to bear the cost of the deployment of the battalion estimated at Rs.112 Crores .

Loktak Downstream Project and Ithai Barrage: The NHPC's push for LDP comes at a time, when indigenous peoples call for review and decommissioning of the controversial Ithai Barrage of the Loktak HEP intensified in Manipur. The NHPC's push for LDP is notwithstanding the appraisal of the Chief Minister of Manipur to the Prime Minister of India on 2 August 2017 to remove the Ithai Barrage to prevent the recurrent flood situation in Manipur .

The Governor of Manipur even join the call to decommission the Ithai Barrage considering the impacts of Loktak HEP project . The NHPC officials conceitedly rebuffed the call of the people of Manipur to decommission Ithai Barrage as emanating from ignorance.

Bedi Ram, the project head of the Loktak HEP project, defended the Ithai Barrage maintaining that the opposition to the Ithai Barrage stemmed from "ignorance" . Such statement of NHPC confirms the irresponsibility and unaccountability of companies like NHPC in Manipur.

The construction of LDP will worsen and prolong the suffering inflicted by Ithai Barrage. The Loktak project instead of irrigating 50,000 hectares of agriculture land submerged more than 50,000 hectares of agriculture land and reducing Manipur to a food dependent state. Villages residing close to Ithai Barrage, such as Laphupat Tera, Khordak Nongmaikhong, Arong, Ithai Wakokpi, Kumbi, Thanga etc complained of repeated flooding and widespread loss of their properties due to the impoundment of water by Ithai Barrage.

NHPC rather than assuming responsibility for the violations and the destruction of Loktak wetlands insisted on construction of additional mega dams in Manipur. The NHPC also downplayed the various academic researches and write ups detailing the Loktak projects' impacts on the people, flora, fauna and culture in Manipur .

The Loktak HEP Project, commissioned in 1983 has been operating for almost Four (4) decades without guidelines on the functioning of the project. There has been no holistic and detailed impact assessment due to the continued operation of both Loktak HEP and the LDP. A continued operation of Ithai Barrage to operate the Loktak downstream project would further devastate Loktak Wetlands, aggravating livelihood loss for communities.

To consolidate profiting from the land and resources of Manipur, the NHPC aggressively pursues the Loktak downstream project. NHPC continues to reap maximum profit while destroying communities' livelihood and Loktak wetlands. Loktak HEP project is major sources of profit for NHPC, but for the people, the project is a simply a symbol of exploitation and plunder of Manipur's land and resources.

Unviability of Hydropower Project: The plan to build the Loktak downstream project need to consider the increased unviability of building large dams. For long, the 66 MW Loktak Downstream Project has been delayed as the NHPC and the Manipur Government failed to sign the PPA, due to high cost of per unit power.

The power tariff of Loktak Downstream Project would be around Rs 6.17 per unit as of 2018, which is comparatively high, prompting Manipur Government to desist from signing PPA with NHPC. When the LDP project was approved by the Government in 1999 at a cost of Rs. 697.67 crores, the corresponding tariff at that time was Rs 4.10 per unit . With the project cost standing around 1500 Crores at 2020, the cost of power per unit cost is slated to increase further.

The per unit price of power from hydel projects is much higher than the solar tariffs, which declined to Rs. 3 in July 2019 as compared to Rs. 4 from hydel power in India . Indeed, India's solar power tariffs hit a record low of Rs 2.36 per kilowatt per hour during a bid by Solar Energy Corporation of India Ltd on 30 June 2020 .

The per unit cost of solar power is set to fall to as low as Rs 1.9 per unit over the next decade through 2030 in India with new technologies boosting efficiency levels . Building hydropower projects is no longer cost effective.

Building a hydel plant can cost Rs 7 to 9 crores per MW, compared with Rs 3.5-4 crores per MW for solar energy. As such, building hydro projects is unviable commercially. One need to ponder the commercial feasibility of large dams like 1500 MW Tipaimukh dam that will requires massive investment of over 10,000 crores rupees by 2020.

Conclusions:

The signing of MoU and PPA for Loktak Downstream project need a clear reflection to address the prolonged demands of the indigenous peoples of Manipur to decommission the Ithai Barrage of 105 MW Loktak HEP Project.

With the Government of Manipur agreeing to purchase the entire power from the Loktak downstream project, the ultimate question is whether it will economical or at a loss of State exchequer. The Government of Haryana refused to purchase power from 1200 MW Teesta III Hydroelectric project due to the high cost the power despite the PPA signed earlier.

NHPC is least bothered of the untold suffering inflicted by its Loktak HEP. NHPC today becomes a perfect symbol of corporate arrogance, blatant disregard of peoples' voices and arbitration of all human rights norms.

Entrusting the rivers, land and forest of Manipur to an unaccountable corporate body like the NHPC to build more dams like the 66 MW Loktak Downstream project and 1500 MW Tipaimukh dam over Leimatak and Barak Rivers would be suicidal for the people and environment of Manipur.

With the push for 66 MW Loktak Downstream Project, NHPC proves its vision of development are detached from the development needs of the people of Manipur. The dismal performance of NHPC, its unaccountability and disrespect of indigenous peoples are reasons rife to restrict it from Manipur.

The construction of LDP project is irrational as the premise of utilizing water discharged from 105 MW Loktak HEP Project would only mean continued suffering of communities and total devastation of Loktak wetlands ecosystem in Manipur.

The Loktak HEP project also failed to provide irrigation water as originally planned, in addition to the livelihood impacts and human rights violations on indigenous communities depending on Loktak wetlands for survival.

The Government of Manipur and Government of India should urgently initiate steps to review and decommission the Ithai Barrage of Loktak project conceding the prolonged demands of the people of Manipur, instead of insisting on construction of another unsustainable dam project.

The Government of Manipur should review and revoke the Power Purchasing Agreement with NHPC, given the high cost and lack of feasibility of the proposed 66 MW Loktak Downstream project. The MoU signed for the project should be revoked. The construction of the project is still pre-mature and the continued operation of 105 MW Loktak Multipurpose Hydroelectric Project and the project together will intensify suffering of communities.

The proposed financing request by the Government of India to Japan International Cooperation Agency for Loktak downstream project should be stopped, considering the larger implications and human rights violations unleashed by hydropower projects in Manipur like the Loktak Project and the Mapithel dam and further, the unaccountability of corporate bodies. The JICA should stop financing dams in Manipur and related supporting infrastructure as mega dams have caused enough hardship, much inconveniences and sufferings to the people of Manipur.

The increased irrationality of hydel projects as energy source amidst the growing viability of alternative options like solar energy need be carefully considered to achieve energy sustainability in Manipur. Destruction of Manipur's land and resources for the profit of irresponsible multinational companies like NHPC should be stopped forever.

The failure and irrationality of dams and wastage of scarce public resources to build such unsustainable projects with multifaceted implications on people and environment in Manipur need be fully reviewed. Recognition of indigenous peoples' development wishes and Self determined rights is crucial in all development decision making and processes.

References :

1. 2020, September 2. Loktak Downstream Hydroelectric Project: LDHCL signs power purchase agreement with MSPDCL. Imphal Free Press.
2. "Feasibility of Loktak Downstream Project discussed in Public Hearing", Kangla Online, 8 June 2011
3. "Loktak Downstream Project likely to take off soon", The Sangai Express, May 9, 2017
4. http://ldhcl.nic.in/?page_id=6
5. Report of the 59th meeting of EAC of the Ministry of Environment and Forest, Government of India, held on 20 - 21st July 2012
6. "Loktak Downstream Project in jeopardy", The Sangai Express, August 23, 2017
7. 27 July 2006. NHPC Pleas Manipur to forsake its share of free power from 90 MW Loktak power project. Infraline
http://www.infraline.com/(S(2it5tc55grtsz445feulwnqn))/power/hydro/Centre/NHPCLoktakHEP.aspx
8. "CMD of NHPC Ltd calls on CM" the Imphal Free Press, 15 December 2017
https://www.ifp.co.in/item/5848-cmd-of-nhpc-ltd-calls-on-cm
9. Loktak Downstream Project in jeopardy, the Sangai Express, 23 August 2017
10. Form A, PWD seeking Forest Clearance from MoEFCC, India for diversion of 72 hectares of forest for road construction for 66 MW Loktak Downstream Hydroelectric project dated 9 August 2012.
http://forestsclearance.nic.in/writereaddata/UploadFormA/51118121612131FormA.PDF
11. Prime Minister's Special Project in Limbo in Manipur, Bit Irom, 21 April 2002
12. 14th June 2020. "Man traceless after falling into river". The Peoples Chronicle
http://www.thepeopleschronicle.in/daily/english/7701
13. (2006). Loktak Downstream HEP. Infraline.
http://www.infraline.com/(S(2it5tc55grtsz445feulwnqn))/power/hydro/Centre/NHPCLoktakHEP.aspx
14. CM Biren calls for review of Loktak project, removal of Ithai barrage NE floods PM announces Rs 2,000 crores relief, the Sangai Express, 2 August 2017.
http://e-pao.net/GP.asp?src=1..020817.aug17
15. "Najma for decommissioning Ithai Barrage, The Sangai Express, 20 September 2017
16. Manipur asks for a review after the ruling BJP wants Loktak hydroelectricity project broken down, 12 August 2017, the Scroll.in
17. "Loktak Lake and Manipuri Lifeworld", edited by Shukhdeba Sharma Hanjabam, A. Koireng and RK Ranjan, published 2014
18. Loktak Downstream runs into PPA wall, the Sangai Express, 12 February 2018
http://www.thesangaiexpress.com/loktak-downstream-runs-ppa-wall/
19. 27 July 2006. NHPC Pleas Manipur to forsake its share of free power from 90 MW Loktak power project. Infraline
http://www.infraline.com/(S(2it5tc55grtsz445feulwnqn))/power/hydro/Centre/NHPCLoktakHEP.aspx
20. "Hydel power in India is growing at the slowest pace", By G Seetharaman, The Economic Times.
21. (2020, July 1). Solar power tariff hits record low, sparks worry about coal's future. Down to Earth.
22. "Solar Power Cost Will Fall to Rs 1.9 Per Unit in India by 2030: TERI", February 14, 2019,


* Jiten Yumnam wrote this article for e-pao.net
The writer can be contacted at mangangmacha(AT)gmail(DOT)com
This article was webcasted on September 28 2020.



* Comments posted by users in this discussion thread and other parts of this site are opinions of the individuals posting them (whose user ID is displayed alongside) and not the views of e-pao.net. We strongly recommend that users exercise responsibility, sensitivity and caution over language while writing your opinions which will be seen and read by other users. Please read a complete Guideline on using comments on this website.




LATEST IN E-PAO.NET
  • Violence in Manipur 2023-2024 : Timeline
  • Attack on fuel tankers & blasting bridge
  • The Happiness Code : Download
  • NH-2 Bridge bombed @Sapermeina : Gallery
  • Crop/animal for higher productivity in NE #1
  • Training Programme under SPARK concluded
  • Why environment control is so difficult
  • 4th Foundation Day- Young Minds Collective
  • All set for second phase poll
  • The Nongsaba phenomenon
  • Khongjom Day @Khebaching #1 : Gallery
  • India's responsibility to end Manipur violence
  • Migrant worker could access TB services only
  • Importance of reading magazines as student
  • SHG pioneering agricultural innovation
  • Nearing the one year mark
  • The enemy within
  • Id-ul-Fitr @Hatta #2 : Gallery
  • Workshop @ NSU Manipur : Gallery
  • 15th Manipur State Film Awards 2023
  • "ST status for Meetei" at Panthoibi Shanglen
  • GSDP doubles, health shines
  • Vote has been cast, repoll held
  • Two faces of democracy
  • Laurels for Scientist Ngangkham Nimai
  • Crime against women in Manipur
  • "ST status for Meetei" at Sugnu
  • Creativity & innovation for vibrant career
  • 4th Foundation Day of YMC
  • Racing towards one year mark
  • Prophetic words, indeed
  • Nupi Landa Thaunaphabishing #14 :: Book
  • 174th Anniv Maharaj Narasingh #1 : Gallery
  • Ensuring Fair Voting in Hills of Manipur
  • Dr Irengbam Mohendra's latest book :: Rvw
  • NDA has the advantage in both
  • Lok Sabha polls in Manipur #1 : Gallery
  • L Rup's Robot 'Kangleinganbi' in Manipuri
  • Art- means of connecting hearts in Manipur
  • Is it Living Alive or Living Death ? :: Poem
  • Rabies - A preventable zoonotic disease
  • April 19, 2024: The blackest day of all
  • Ugly turns on voting day
  • Children Camp @JNMDA Imphal #2 : Gallery
  • The chasm between TB & HIV continues
  • Parliament and its Members
  • Kimchi for health and glowing skin
  • LS election with a difference
  • To vote, or not to vote ?
  • Sajibu Cheiraoba Chak Katpa #2 : Gallery
  • "ST status for Meetei" at Lamjao, Kakching
  • The Power of Poppy - 27 :: Poem
  • Mother Language based education essential
  • Modi's warriors wear regional hats
  • Nest Asia promoting Northeastern Cuisine
  • Now look beyond LS poll
  • The rot in the system
  • Scientists of Manipur : Laitonjam Warjeet
  • Community seed bank @Umathel : Gallery
  • 10 candidates cracked Civil Services Exam
  • Milk of Paradise: History of Opium : Rvw
  • How plastics find their way into our bodies
  • Condemning attack on Trucks along NH-37
  • Cong looking to buck the trend
  • Saving Manipur
  • Sajibu Cheiraoba: 1 occasion, 2 narratives #2
  • Election Duty :: Travellog
  • 1st Nagas' Meet in Punjab
  • How to select right MP to represent Manipur
  • "ST status for Meetei" at Tejpur
  • Bats are Keystone species for the Planet
  • The '15 days' conundrum
  • Free but not so fair
  • Descent of Radha-Krishna #30: Download
  • Before You Vote : My Rumbling Thoughts
  • "ST status for Meetei" at Kakching
  • Meiraba wins All India Sr tournament
  • Finding light in dark through my daughter
  • Navigating life's unreasonable expectations
  • Test of people's character
  • BJP's election manifesto
  • Athoubasingi Numit #1 : Gallery
  • Black rice & Glycemic Index
  • What Nadda should speak at Dimapur rally
  • Open Letter to CM Office Manipur
  • Meghalaya unveils Strawberry festival
  • Benefits of maths newspapers for students
  • Id-ul-Fitr @Hatta #1 : Gallery
  • Are you a good person ?
  • Physics Academy of NE : Executive Body
  • "ST status for Meetei" at Moirang
  • Cherrapunji Eastern Craft Gin launched
  • Cong on cautious path
  • Botox for Hair
  • Posers voters should raise now
  • The lull before the storm
  • 80th Anniv- Battle of Kanglatongbi @UK
  • Vir Chakra Ngangom Joydutta's bust unveiled
  • Hun - Thadou Cultural Festival : Gallery
  • "ST status for Meetei" at Singjamei
  • Election Eclipses: Ballad of Battle & Loss
  • Our voices are equal at the ballot box
  • Scientists of Manipur : Ngangkham Nimai
  • Urgent Call for Solidarity in Manipur
  • Meitei Nongsha #2 :: An Artwork
  • "ST status for Meetei" at Waikhong
  • About NPF-BJP-NPP alliance & why ?
  • World Veterinary Day, 2024
  • The heavy stake behind the LS polls
  • The politics of lying & deception
  • Sajibu Cheiraoba Chak Katpa #1 : Gallery
  • Hun-Thadou Cultural Fest @ Delhi: Report
  • Appeal to Parties & Candidates
  • "ST status for Meetei" at Wangoo
  • Establishment of community seed bank
  • Awareness Programme on new Criminal Laws
  • Make a right choice at the Lok Sabha election
  • Sajibu Cheiraoba: 1 occasion, 2 narratives #1
  • RIST talk-58 : Support systems of elderly
  • "ST status for Meetei" at Hiyanglam
  • Vote, do not boycott !
  • Lok Sabha election: A new dawn in politics ?
  • IIT-Guwahati Half Marathon report
  • Taking ST demand to the election ring
  • Lesson to be learnt from across border
  • Mirabai: Poised for Paris Olympics
  • Legal position for protection of environment
  • "ST status for Meetei" at Keisamthong
  • Heterocyclic compound & biochemical science
  • Inner, torn between two lovers
  • Certification Music Therapy Workshop
  • NOTA as a choice
  • Caesar's wife must be above suspicion
  • Descent of Radha-Krishna #29: Download
  • World Health Day 2024
  • "ST status for Meetei" at Pangantabi
  • The Power of Poppy - 26 :: Poem
  • Fulbright Fellowship Outreach at Arunachal
  • Id-ul Fitr da namaz nattana..
  • Nupi Landa Thaunaphabishing #13 :: Book
  • Lok Sabha election is coming, be prepared
  • 6th Hun-Thadou Cultural Festival
  • Let There Be Free & Fair Election
  • "ST status for Meetei" at Lamlong
  • Science magazines are important for student
  • Interesting choice of candidates
  • The power of We, the voters
  • Inspirations from Scientists of Manipur #1
  • The Case for Amendment of Article 371-C
  • Meitei Nongsha #1 :: Artwork
  • Link between forest & conflict in Manipur
  • Final Call for Application MFA - Phase-2
  • ST for Meiteis call before elections
  • Passing the buck
  • Beating of the Retreat #1 : Gallery
  • Life of our Lives in Ethnic Strife Era! :: Poem
  • IIT-Guwahati annual Half Marathon
  • Follow up: European Parliament on Manipur
  • Yoga & Kegel exercise: Pelvic floor workout
  • Opting for the NOTA button
  • Yearning of the displaced people
  • Kenedy Khuman (Singer) : Gallery
  • 5th NE Women's Peace Congregation
  • World Autism Awareness Day 2024
  • Election fever grips Manipur despite unrest
  • Looking for a decent election hustings
  • Clock ticking towards voting day
  • An exemplary directive
  • Children Camp @JNMDA Imphal #1 : Gallery
  • Memo to Election Commission of India
  • Easter & Holi echo in Nilgiris
  • Holiday Camp for children at JNMDA, Imphal
  • Zero waste is our moral responsibility
  • Elections & loyalty vis-a-vis Manipur crisis
  • Show of strength without unity
  • Yaoshang Pichakari #2 : Gallery
  • Panthoi Chanu : 1st to play in Australia
  • Intensive labs in film preservation
  • Building bridges with books
  • Need of the hour: Political maturity
  • Accepting defeat before the election
  • Descent of Radha-Krishna #28: Download
  • April Calendar for Year 2024 : Tools
  • Natural packaging from bamboo : Gallery
  • The Power of Poppy - 25 :: Poem
  • Everyone has their own Bharat Ratna
  • Nupi Landa Thaunaphabishing #12 :: Book
  • Demand- Manipuri as classical language
  • The Drummer from Odisha
  • Beauty benefits of lemon
  • Yaoshang Mei Thaba #2 : Gallery
  • Manipur's original Ponies : Gallery
  • Yaoshang & Dance of Democracy loom
  • Symposium on Jagadguru Shankaracharya
  • Choosing ITI as a campus after X
  • Yaoshang Pichakari #1 : Gallery
  • Yaoshang @Nabadwip Dham : Gallery
  • How oral health affects your pregnancy
  • Two faces of Holi
  • Prawaas 4.0, Multimodal Transport Show
  • A decade of development of higher education
  • Yaoshang Mei Thaba #1 : Gallery
  • Our Eternal Kangleipak :: Poem
  • Micro-livestock for livelihoods: For NE States
  • The fun of Holi used to be monotonous
  • 2nd Annual Art Exhibition #1 : Gallery
  • About the "Meitei" community from Manipur
  • Unveiling the medicinal benefits of honey
  • The incalculable value of wildlife
  • Promises of true love
  • Trends, Alliances, & Challenges in Elections
  • Meitei Goddess Ngaleima : An Artwork
  • Lamta Thangja @ Imphal : Gallery
  • Meira Paibis of Manipur
  • North East Film Festival #2 : Gallery
  • Students @ Class X Exam : Gallery
  • Saroi Khangba @ Kangla : Gallery
  • Protest for scrapping SoO #2 :Gallery
  • Shopping List for Shivaratri : Gallery
  • N Tombi Equestrian C'ships #1 : Gallery
  • Featured Front Page Photo 2024 #1: Gallery
  • Radio E-pao: Manipuri Film OST (130+ song)
  • Save Manipur : Protest [Feb 15] #3 : Gallery
  • Naorem Roshibina- Wushu Medallist : Gallery
  • GHOST of PEACE :: Download Booklet
  • List of Kings of Manipur: 33 - 1984 AD